reconstruction of the airport began in May 2010 and be completed in 2012. Total investment in the development of the airport will be more than 1 billion hryvnia.Reconstruction of the airfield infrastructure includes: construction of a new runway , repair existing runway and existing taxiways, apron reconstruction , lighting and radio navigation systems.
A new runway ( 3260h60 m) will be longer and wider than the existing ( 2850h44 m ), located parallel to the existing zone at 150 meters from it (towards the passenger terminal ).
reconstruction and repair of the apron , taxiways - will be carried out with increased coverage and increase their carrying capacity.Platform will be significantly expanded its area will increase by 75%, additional parking will be built for medium-and long-haul aircraft will increase the total number of aircraft parking areas .
In May 2010,preparations began for the construction of a new international passenger terminal , whose construction is scheduled for completion in 2012.
The new facility , located on the south-west of the existing terminal, significantly increase the possibilities airport. It will be built in two levels, divided into zones of arrival and departure passengers.The capacity of the new terminal will be about 1,000 people per hour . In this case the existing terminal in the future will serve only domestic flights. The combined capacity of two terminals exceeds 1,500 passengers every hour, the press service of OJSC AK Dniproavia .
--- .